Mohan can do a piece of work in 10 days working 8 hours per day.in how many days can he do the same work by increasing his working hours by 2 hours per day??
Answers
Answered by
0
Answer:
8 days
Step-by-step explanation:
As,
10×8= 80
80 by 10 = 8 days