Mohan do a work in 9 hour .Mohan and sohan both do a work in 5 hour tell that how much time sohan will take to do it (formula)
Answers
Answered by
1
Answer:
you can do it by taking x or by direct and inverse variations
Answered by
0
Answer:
1/9+1/x=1/5
Step-by-step explanation:
(x+9)/9x=1/5
5=9x/(x+9)
5x+45=9x
4x=45
x=45/4=11.25 hours