Math, asked by sreevardhanreddy7, 10 months ago

Mr. A, Mr, B and Mr. C are assigned a project as a team. Mr. A and Mr. B can finish the project together in 30 days, while Mr. B and Mr. C together in 24 days and Mr. C and Mr. A in 20 days. They all worked together but due to poor performance, Mr. B and Mr. C were eliminated from the team after 10 days. How many more days does Mr. A need to finish the project?

Answers

Answered by nikhil4719
0

Answer:

MR A need 40 days

Step-by-step explanation:

Because MrA and MrC =20dats

MRA AND MRB =30

20+30=50

50_10=40