Math, asked by hua139, 6 months ago

One man takes one day to dig a 4 m
long trench. How long would it take
2 men working at the same rate to
dig a 16m long trench?
B. 2 days
A. 1 day
C. 4 days
D. 8 days​

Answers

Answered by Anonymous
2

Given,

One man can dig a 4 metres long trench in one day.

To find,

The number of days that will be taken by 2 men to dig a 16 metres long trench.

Solution,

We can easily solve this mathematical problem by norrmal arithmetic method.

1 man can dig 4m trench in = 1 day

1 man can dig 1m trench in = 1/4 day

1 man can dig 16m trench in = 16/4 = 4 days

2 men can dig 16m trench in = 4/2 = 2 days

(Division and multiplication are done according to the direct or inverse proportion.)

Hence, it will take 2 days (option B).