Math, asked by AbhinavDeep4644, 10 hours ago

Out of 24 machines, half of them works 10 hours a day and finishes the work in 5 days.
How many days will 20 machines takes to complete the job, working six hours daily?

Answers

Answered by vikkiain
0

Answer:

5 days

Step-by-step explanation:

Given,

M1=24/2 =12, H1=10 and D1=5

M2=20, H2=6, then D2=?

use, M1D1H1 = M2D2H2 formula

12x10x5 = 20xD2x6

600 = 120xD2

D2 = 600/120 = 5