P and Q can do a piece of work in 45 and 40 days respectively. They began the work together but P leaves after some days and Q finished the remaining work in 23 days. Then Q has worked for:
A) 9
B) 21
C) 32
D) None of these
Answers
Answered by
1
A does the job in 45 days = 1/45
B does the job in 40 days = 1/40
A & B together completes the job = ?
After A leaves, B completes the remaining job in 23 days.
i.e B's part of job in 23days = 23/40
Remaining part 17/40 is done by A & B together in x no.of days.
i.e (x/45) + (x/40) = 17/40
==> x = 9 days
Soln:
A leaves after 9 days