P
and
Q
can finish a piece of work in
35
days and
31
days, respectively. P started the work and worked at it for
13
days. He was then joined by
Q
. Find the total time taken to finish the work.
Answers
Answered by
21
Answer:
This question is a reference to your question , you can take help of this to find your answer
Let A's 1 day's work = x and B's 1 day's work = y.
Both A's and B's 1 day work=1/30
i.e (A's 1 day + B's 1 day)=1/30
i.e x + y = 1/30........eq1
now,
A having worked for 16 days, B finishes the remaining work alone in 44 days
i.e work done by A in 16 days = 16x
Remaining work done B= 1 - 16x
but Remaining work is done by B in 44days i.e 44y
i.e. 44y=1-16x
i.e 16x+44y=1........eq2
solving eq1 & eq2,
we get,x = 1/60 and y = 1/60
B's 1 day's work = 1/60.
Hence, B alone shall finish the whole work in 60 days.