P and q together can complete a work in 12 days. P alone can complete in 20 days. If q does the work only half a day daily, then in how many days p and q together will complete the work?
Answers
P ans Q Work together is :
P + Q complete a piece of work in 12 days
P complete a piece of work in 20 days
First we take LCM of these numbers 12 , 20
so, LCM is 60 ( total work is 60 )
P + Q complete whole work in 12 days and total work is 60
then P + Q complete work in 1 day = 60/12 = 5 (efficiency of P + Q )
P complete whole work in 20 days and total work is 60
then P complete work in 1 day = 60/20 = 3 (efficiency of P )
now ,
Efficiency of P is 3
and Efficiency of P + Q is 5 ( P = 3)
so, Q = 2 ( in 1 day )
but according to question, it says that q does the work only half a day daily
so Q = 2/2 = 1
now , P + Q = 3 + 1 = 4
so , total work = 60
P + Q = 60/4 = 15 day
Know more
Q.1.- If man A complete a piece of work in 12 days and the same work is completed by B and C in 15 days and 20 days respectively. In how many days the work is completed if they work together?
Click here- brainly.in/question/14963073
Q.2.- A and b can complete a work in 12 days together, b and c can complete the same work in 15 days together and a and c can complete that work in 20 days together. in how many days a can complete the same work alone?
Click here- brainly.in/question/1744674
Q.3.- A and b can do a piece of work in 6days b and c in 8days a and c in 12days if they work together and a leaves after 4days how many days remaining b and c complete
Click here- brainly.in/question/9044993