P and R working together can finish a work in 10 days. If P works for 4 days then remaining work is completed in 15 days by R. Q is 2/3rd as efficient as R. Find the time taken by Q and R to do the same work if they are working together.
Answers
Answer:
Q and R working together can finish the same work in 11 days
Step-by-step explanation:
Let the amount of work done by P in 1 day = 1/p
Amount of work done by Q in one day = 1/q
Amount of work done by R in one day = 1/r
Since Q is 2/3 as efficient as R
Therefore
1/q = 2/3 × 1/r
Again
In 1 day P and R together can finish = 1/p + 1/r work
In 10 days P and R can finish = 10(1/p + 1/r) work
According to the question
10(1/p + 1/r) = 1
or 1/p + 1/r = 1/10 ..... (1)
In 4 days work done by P = 4/p
Remaining work = 1-(4/p)
This work is completed by R in 15 days
Therefore,
15/r = 1 - 4/p
or 15/r + 4/p = 1 .......... (2)
Multiplying eq (1) by 4 and subtracting from eq (2)
15/r - 4/r = 1 - 4/10
or, 11/r = 6/10
or, 1/r = 3/55
Let the number of days required by Q and R to finish the work is x
Then
x(1/q + 1/r) = 1
or, x(2/3r + 1/r) = 1
or, x/r(5/3) = 1
or,
or, x = 11
Therefore, Q and R working together can finish the work in 11 days