P can complete a piece of work, working alone in 3 days.q can complete the work in 5 days.if they work in alternate days the work would be completed in least number of days if
Answers
Answered by
0
P completes one - third of the work in a day
Q completes one-fifth of the work in a day
They work alternate days. So in every 2 days they complete: 1/3 +1/5 = 8/15 of the work
Let us consider 2 days as a single unit.
So, we need 15/8 such units to complete the work. That is 1.875
1.5 unit means 3 days and 1.875 is higher than 1.5
So we need minimum 4 days
Q completes one-fifth of the work in a day
They work alternate days. So in every 2 days they complete: 1/3 +1/5 = 8/15 of the work
Let us consider 2 days as a single unit.
So, we need 15/8 such units to complete the work. That is 1.875
1.5 unit means 3 days and 1.875 is higher than 1.5
So we need minimum 4 days
Answered by
0
Answer:
Least Number of days required is 4 days of work.
Explanation:
What is Unitary Methord ?
The unitary method involves calculating the value of a single unit, from which we can calculate the values of the necessary number of units.
P's one day work =
Q's one day work =
If they Work alternatively (P+Q)'s 2 days work = parts
So finish the work time required = days
Least Number of days required is 4 days of work
To learn more about Unitary Methord refer to :
https://brainly.in/question/12383836?referrer=searchResults
https://brainly.in/question/9475359?referrer=searchResults
#SPJ2
Similar questions
Social Sciences,
7 months ago
English,
7 months ago
Math,
1 year ago
Social Sciences,
1 year ago
Math,
1 year ago
Social Sciences,
1 year ago