p can complete a work in 12 days working 8 hours a day if you can complete the same work in 8 days working 10 hours a day if both p and q work together working 8 hours a day in how many days can they complete the work​

Answers

Answered by gautaminda3547
2

Step-by-step explanation:

If both P and Q work together, working 8 hours a day, P can complete the work in (12 x 8) hrs. = 96 hrs.

Answered by XxShAnTaNuxX
1

\huge \underline \frak \pink {★彡A᭄ɴsᴡᴇʀ彡★}

\huge \red{5\frac{5}{11}}

\large\colorbox{orange}{May Be Helpful ✌️ Dear ✌️}