P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?

Options
1) 8
2) 5
3) 4
4) 6

Answers

Answered by shreyansgarg2004
1

Answer: 6 days

Step-by-step explanation:

If Q can do complete work in 15 days. Then in 10 days he will be able to do

10/15 = 2/3 of the work.

Work left = 1-2/3

= 1/3.

If P cancn do work in 18 days, he can do remaining (1/3) work in:

(1/3) × 18

= 6 days