Math, asked by shreya948010, 1 year ago

P+Q can complete a work in 30 days. They start work together and after 23 days Q left the work and whole work complete in 33 days. Find the time in which p alone complete the work.

Answers

Answered by IamIronMan0
1

Answer:

 \frac{300}{7}  \: days

Step-by-step explanation:

given

 \bigg( \frac{1}{p}  +  \frac{1}{q}  \bigg)30 = 1  \\ 33. \frac{1}{p}  + 23. \frac{1}{q}  = 1

q complete the work in 100 days