Math, asked by khanrk783, 1 year ago

Paul and peter can do a piece of work in 60 days, while paul can do it alone in 80 days. how many days will peter take to complete the work alone?

Answers

Answered by inhumandrowsey
6

Paul and peter together can do it in 60 days, 1 day work = 1/60

Paul can do it in 80 days, 1 day work = 1/80


1 day work of peter = 1/60 - 1/80 = (4-3) / 240 = 1 / 240

Peter will take 240 days




Answered by TooFree
4

Paul and Peter can do the piece of work in 60 day

⇒ 1 day = 1/60 of the work


Paul can do it alone in 80 days

⇒ 1 day = 1/80 of the work


Find the amount of work Peter can do in a day:

1 day = 1/60 - 1/80 = 1/240


Find the number of days Peter will need to complete the work:

1/240 of the work = 1 day

240/240 of the work = 1 x 240 = 240 days


Answer: Peter can do the work in 240 days alone.