Please answer as many questions
Attachments:
Answers
Answered by
2
Step-by-step explanation:
solution.. let 20 workers will requires x days to complete the job .
10/ 20 = 6/x croSs multiply..
10*x=20*6
x = 120/10
x= 120/10
x= 12
lhence the ans 20 workers will requires 12days to finish the same job
I hope it will help u mark me
ask only one question
I solve1) a