please answer it if you can
Attachments:
Answers
Answered by
2
Answer:
18 days
Step-by-step explanation:
engineer said he could finish highway sector in 3 days
Let us suppose that he had X machines
so with X machines he took 3 days to complete the work
Again given that if 3 more machines were used then completes in 2 days
so in 2 days X+3 machines work will be = 3 days with X machines
==> 2 ( X + 3 ) = 3 X
==> X = 6 machines
so from this total work is 3X parts = 3 × 6 = 18
if we make with one machine 18/1 = 18 days