Answered by atulkumarsingh711
0
the right answer is 4days
Answered by hermionegranger19
0
Let us take the total work to be 1
So, Ram takes 12 days to do the total work.
So, 1 day of work for Ram= 1/12 of the work.
Meanwhile, Amir takes 6 days to do the total work.
So, 1 day of the work for Amir =1/6 of the work.
So, together=1/12+1/6
LCM of 12 and 6