Math, asked by REDMAM, 10 months ago

please answer the me this question​

Attachments:

Answers

Answered by arvinddashora
1

Answer:

Step-by-step explanation:

Rohan can paint 1/3 of painting in 6 days

So,

Rohan can paint his painting in 6*3 = 18 days

Mark BRAINLIEST...

THANKS...

Answered by Ayushp08
1

Answer:

In 6 days, one third of the work is completed

1/3 = 6 days

3/3 = 6×3 days

1 = 18 days

Therefore, it would take 18 days to complete the work.

Similar questions