Math, asked by nicyrans, 6 months ago

please answer this question​

Attachments:

Answers

Answered by babykutush2004
1

Answer:

60 MEN

Step-by-step explanation:

In 75 days , a work is done by= 48 men

Therefore , In 1 day ,the work is done by =75 X48 men

In 60 days , the work will be done by =\frac{75 *48}{60} \\60 men

Answered by akhtermchari
0

Answer:

60 men

Step-by-step explanation:

     In 75 days a building can construct by 48 men

so, In   1     ''      ''    ''            ''         ''           ''  (48×75) Men

so, In   60  ''      ''    ''            ''         ''           ''  {3600\over 60}  Men

                                                                     =60 Men    