Math, asked by MERCURY1234, 1 year ago

PLEASE ANSWER THIS QUESTION

A and B can complete a piece of work in 15 days and 10 days respectively. They work together for 4 days and then B leaves. In how many days will A alone complete the remaining work?

BRAINLIEST QUESTION

Answers

Answered by gaurav2013c
4
A can do the work in 15 days

A's one day work = 1/15

B can do the work in 10 days

B's one day work = 1/10

( A + B)'s one day work = ( 1/15 + 1/10)

= ( 2 + 3) / 30

= 5 /30

= 1/6

( A + B)'s four days work = 4/6 = 2/3

Left work = 1 - 2/3 = 1/3

Now,

Number of days Required for A to finish the work = ( 1/ 3) / (1/15)

= 15 /3

= 5 days


MERCURY1234: tnx
MERCURY1234: please answer my another question
MERCURY1234: plz bro
MERCURY1234: vry fast
gaurav2013c: someone already answered
MERCURY1234: now plz answer
MERCURY1234: plez
MERCURY1234: fast
Similar questions