Math, asked by MERCURY1234, 1 year ago

PLEASE ANSWER THIS QUESTION

A, B and C can complete a piece of work in 25, 30 and 50 days respectively. They started the work together but A and C left 2 days before the completion of the work. In how many days will the work be completed?

BRAINLIEST QUESTION

Answers

Answered by NAVEEN11234
2
The answer is 16

Hope it helps!!