Math, asked by rawattanisha409, 1 month ago

please give me answer
I will mark you brain list ​

Attachments:

Answers

Answered by patimanas129
0

Answer:

I think it will be helpful for you

Attachments:
Answered by bhagyashreelisha08
0

Answer:

20 men can complete a work in 4 days.

1 man can complete the work in 20*4 days= 80 days.

16 men can complete a work in 80/16 = 5 days.

Hence, In 5 days 16 men can complete the work.