Math, asked by mvlikhith, 1 year ago

Please help me the problem is a work force of 50men with a contractor can finish a piece of work in 15 months in how many months the same work can be completed by 125men? Please give me your answer by step by step

Answers

Answered by SillySam
3
Time taken By 50 men to finish a work = 15 months

This question is of inverse proportion. As when men will decrease, time taken to complete the work will increase.

Time taken by 1 man to finish a work = 15×50 months (inverse proportion)

= 750 months

Time taken by 125 men =750/125

= 150/25

= 30/5

=6 months

Or 6×30 = 180 days (approx)


mvlikhith: Tq
SillySam: my pleasure:)
Answered by siddhartharao77
3

Answer:

6 months

Step-by-step explanation:

Given that 50 men do the work in 15 months.

Then, 1 men can do the work in 50 * 15 months.

125 men can finish the same work in:

= (50 * 15)/125

= 750/125

= 6 months.


Therefore, 125 men can finish the same work in 6 months.


Hope it helps!