Math, asked by lili8595, 10 months ago

please solve this .....
I was already asked this 4 times​

Attachments:

Answers

Answered by koushik2653
0

Answer:

5.9 days

Step-by-step explanation:

because he is a man

Answered by pentagon5solution
1

Answer:

Example Women Power =w , Man Power = m

Men               Women          Days           Project

5                        2                   4                    100%

6                        3                   3                    100%

(5m+2w)4 = 1

(6m+3w)3 = 1

(5m+2w) = 1/4              ----. 3

(6m+3w) = 1/3              ----.2

15m+6w = 3/4

12m+6w = 2/3

------------------------------   -

3m = 1/12

m = 1/36

a man need 36 days to finish an embroidery

12.1/36 +6w =2/3

6w = 1/3

w = 1/18

a woman need 18 days to finish an embroidery

Step-by-step explanation:

Similar questions