Given, Workers take time to load 15 trucks = 8 hours.
Then one truck is loaded in = 8/15 hours .
Time taken for loading 2 trucks = 8/15 * 2 hours.
= 16/15
= 1 1/15 hour
= 1 hour 4 mins.