25 labours can complete a building in 8 months. how many labours will be required to contract another building of triple size as that of previous building in 10 months?
Answers
Answered by
0
60 workers.
8*3=24
24/10=2.4
25*2.4=60
;)
8*3=24
24/10=2.4
25*2.4=60
;)
Answered by
1
8 × 3 = 24
24 × 2.4 = 60