Math, asked by TRISHNADEVI, 1 year ago

Plzz..Solve the question by the above method

A contractor undertakes a work to comple in 90 days.He first employs 152 men who worked 6 hours a day and finished 3/4 of the work in 75 days.How many more men should he employ to finish the work in specified time if day work for 8 hours a day.

Attachments:

Anonymous: if noone answers i will
akay75: hello
akay75: how r you

Answers

Answered by shyamkrishnakeshari
2
hey Trishna..
take your solution..
In your book have done the solution by the fomula but nothing is mention..
so plz try to understand...
see my solution..in this image..
I hope you understand °^°
Attachments:

shyamkrishnakeshari: whatvis the value of M2
shyamkrishnakeshari: tell me plz
shyamkrishnakeshari: oh Yani 190
shyamkrishnakeshari: used the same formula or any other method
shyamkrishnakeshari: are u enjoy that formula
Answered by Chhavibansal
0
Heya!!!
Here your answer is...

25 men can complete 1313 work in 24 days

Suppose xx men can complete 2323 work in 12 days

25×2413=x×1223 25×24=x×122 x=10025×2413=x×1223 25×24=x×122 x=100

Required extra men =100−25=75=100−25=75

HOPE IT WILL HELP YOU.. ✌ ✌
IF SO THAN MARK IT AS BRAINLYT...
Similar questions