Plzz..Solve the question by the above method
A contractor undertakes a work to comple in 90 days.He first employs 152 men who worked 6 hours a day and finished 3/4 of the work in 75 days.How many more men should he employ to finish the work in specified time if day work for 8 hours a day.
Attachments:
Anonymous:
if noone answers i will
Answers
Answered by
2
hey Trishna..
take your solution..
In your book have done the solution by the fomula but nothing is mention..
so plz try to understand...
see my solution..in this image..
I hope you understand °^°
take your solution..
In your book have done the solution by the fomula but nothing is mention..
so plz try to understand...
see my solution..in this image..
I hope you understand °^°
Attachments:
Answered by
0
Heya!!!
Here your answer is...
25 men can complete 1313 work in 24 days
Suppose xx men can complete 2323 work in 12 days
25×2413=x×1223 25×24=x×122 x=10025×2413=x×1223 25×24=x×122 x=100
Required extra men =100−25=75=100−25=75
HOPE IT WILL HELP YOU.. ✌ ✌
IF SO THAN MARK IT AS BRAINLYT...
Here your answer is...
25 men can complete 1313 work in 24 days
Suppose xx men can complete 2323 work in 12 days
25×2413=x×1223 25×24=x×122 x=10025×2413=x×1223 25×24=x×122 x=100
Required extra men =100−25=75=100−25=75
HOPE IT WILL HELP YOU.. ✌ ✌
IF SO THAN MARK IT AS BRAINLYT...
Similar questions