Priya and meena alone can complete a work in 15 days and 20 days respectively, if they do that work together for 4 days then what is the amount of work left if the total work is for 225 units
manju991970:
answer please
Answers
Answered by
7
Total work is 225 units
Priya works for 15 days. So, she does 15 units of works everyday which completes 225 units of work in 15 days
i.e 225 units/15 days=15 units/day
Meena works for 20 days. So, she does 11¼ units of works everyday which completes 225 units of work in 20 days
i.e 225 units/20 days=11.25 units/day
Meena and Priya together do 26.25 units of work in a day. If they work for 4 days together, they would complete 105 units of work.
i.e 26.25 units*4=105 units
Total work is 225 units
After subtracting 105 units from total work, 120 units of work will be remaining.
The answer is 120 units.
Hope it helps.
Priya works for 15 days. So, she does 15 units of works everyday which completes 225 units of work in 15 days
i.e 225 units/15 days=15 units/day
Meena works for 20 days. So, she does 11¼ units of works everyday which completes 225 units of work in 20 days
i.e 225 units/20 days=11.25 units/day
Meena and Priya together do 26.25 units of work in a day. If they work for 4 days together, they would complete 105 units of work.
i.e 26.25 units*4=105 units
Total work is 225 units
After subtracting 105 units from total work, 120 units of work will be remaining.
The answer is 120 units.
Hope it helps.