Q. 13 A and B finish a work in 8 days, B and c finish same work in 12 days. A alone can find finish the same work in 16 days. How much time C alone could take to finish the Same work ?
Answers
Answered by
1
Answer:
A plus B one day work equal 1 by 8
b+ c one day work equal 1 by 12
A one day work equal 1 by 16
c one day work equal 1 by 8 - 1 by 12 equal 1 by 24 equal 24 days