Q. 13 A and B finish a work in 8 days, B and c finish same work in 12 days. A alone can find finish the same work in 16 days. How much time C alone could take to finish the Same work ?​

Answers

Answered by ssksony452
1

Answer:

A plus B one day work equal 1 by 8

b+ c one day work equal 1 by 12

A one day work equal 1 by 16

c one day work equal 1 by 8 - 1 by 12 equal 1 by 24 equal 24 days