Q 24 Ray can complete a piece of work in 15 days. What percent of work will he complete in 7.5 days?
Ops: A.
O 30%
20%
60%
D. O 50%
Answers
Answered by
2
Answer:
(d) 50 %
Step-by-step explanation:
it is because 7.5 is half of 15 so the ans will be 50%
please mark it as the Brainliest
Answered by
0
Given: Ray can complete a piece of work in 15 days.
To find: We have to find the percentage of work that will be completed in 7.5 days.
Solution:
Let the total work be 100 units.
In 15 days Ray can complete 100 units of work.
Thus in 7.5 days, Ray can complete 100×7.5/15=50 units of work.
Total work is 100 units.
Work completed 50 units.
Thus the percentage of work completed is-
Thus 50% of work has been completed in 7.5 days.
The correct option is D.