Math, asked by yanak201206, 1 month ago

q 6) 52 workers complete piece of work in 35 days. in how many days 28 workers do it? *
1 point
40 days
72days
65 days
48days​

Answers

Answered by straightforward
2

Step-by-step explanation:

52 \: workers  -  35 \: days \\ 28 \: workers \:  - x \\ small \: number \: of \: people \: would \: surely \: need \: more \: days \\ this \: is \: a \: case \: of \: inverse \: proportion \\  \frac{52 \times 35}{28 \times x}  \\ x =  \frac{52 \times 35}{28}  \\ x = 65 \: days

Pls Mark this answer as the brainliest

Similar questions