Q5. 20 persons can do a piece of
work in 7 days, then the number
of persons required to complete
the work in 28 days is​

Answers

Answered by TheIronGirl
7

Answer:

MARK AS BRAINLIEST

Step-by-step explanation:

If 20 person can do a piece of work in 7 days, then how many person is required to complete the work in 28 days?

Answer: This job can be completed in 28 days by 5 persons.

Measured work content 20 persons x 7 days = A total work content of 140 days work

140 days work + 28 days = 5 persons

Answered by barbie200721
3

Answer :

80

Step-by-step explanation:

7 --> 20

28 --> (28×20)÷7

= 560÷7

= 80