Question 9:- Tanu Ltd. uses predetermined overhead rate of Rs. 15 per labour hour, the actualoverhead cost is Rs. 85,000 and actual labor hour are 5,750. The under or over absorption ofoverhead is:a) Rs 1,250 (over)b) Rs 1,250 (under)c) Rs 1,000 (over)d) Rs 1,000 (under)
Answers
Answered by
0
Answer:
b( rs 1250