Math, asked by hafeeza97, 10 months ago


Question:
A&B can do a job in 12 days, B & C in 15 days and C&A in 20 days. How long would A take to do that work?

Answers

Answered by VaibhavTheAryabhatta
2

Answer:

(a + b) \: 1 \: day \: work \:  =  \frac{1}{12}  \\  \\ (b + c) \: 1 \: day \: work =  \frac{1}{15}  \\  \\ (c + a) \: 1 \: day \: work =  \frac{1}{20}  \\  \\ 2(a + b + c) \: 1 \: day \: work =  \frac{1}{12}  +  \frac{1}{15} +  \frac{1}{20}  =  \frac{5 + 4 + 3}{60}   =  \frac{12}{60}  =  \frac{1}{5}  \\  \\ a \: 1 \: day \: work \:  =  \frac{1}{5} -  \frac{1}{15} =  \frac{3 - 1}{15}  =  \frac{2}{15} \\  \\ answer =  \frac{15}{2}  = 7 \frac{1}{2} days