Ram can do a work in 6 days and Ramesh can do the same work in 9 days. They work together for 3 days. Ram left the work then(a) In how many days can Ramesh will do the remaining work along? (b) How many days are needed to complete the whole work
Answers
Answered by
0
Answer:
a. 3 days
sorry I didn't no b
Answered by
1
Answer:
Step-by-step explanation:
Ram = 6
Ramesh = 9
Total work = 18
Efficiency = 2 & 3
5e× 3d = 15 w
Remaing = 3w
3 w with 2e = 1(1/2) days
A)=1(1/2)
B)=4(1/2) days