Ram completes a work in 18 days. Ram and rohan together complete the work in 6 days. How many days it will take for rohan alone to complete the same work?

Answers

Answered by sweetyadabala91
2
Ans : 6days

Hope it will be helpful to you.
Answered by wifilethbridge
0

It will take 9 days for rohan alone to complete the same work

Step-by-step explanation:

Ram completes a work in 18 days

Ram's 1 day work = \frac{1}{18}

Ram and rohan together complete the work in 6 days.

Ram and rohan together work in 1 day = \frac{1}{6}

So, Rohan's 1 day work = \frac{1}{6}-\frac{1}{18}=\frac{2}{18}=\frac{1}{9}

So, Rohan can compete work in days = 9

Hence it will take 9 days for rohan alone to complete the same work