Raman and Bishnu can do a piece of work in 20 days and 15 days respectively. Raman started the work alone and then after 4 days Bishnu joined him till the completion of the
work. How long did the work last?
O 48/7
O 76/7
040/7
0 43/7
Answers
Answer:
option C is correct.....
Given:
Days required by Raman to complete a work = 20 Days
Days required by Bishnu to complete a work = 20 Days
To find:
Days for which work lasted.
Solution:
One day work of Raman = 1/20
One day work of Bishnu = 1/15
Initially, Raman worked for 4 days alone,
Work done by Raman in 4 days alone = 4/ 20 = 1/5
Remaining work = 1 - (1/5)
Remaining work = 4/5
Now, 4/5 part of the job was done by both Raman and Bishnu.
One day work of Raman and Bishnu = +
part of job completed in one day by Raman and Bishnu = 7 / 60
Days required to complete one job = 60/7 days
Days required to complete 4/5 part of the job = (4/5) × ( 60/7)
Days required to complete 4/5 part of the job = 48/7
Hence, the total days for which work lasted is 48/7 days