Math, asked by ckchinkusharma59, 4 months ago

Ramesh and Ganesh can together complete a work in
16 days. After seven days of working together,
Ramesh got sick and his efficiency fell by 30%. As a
result, they completed the work in 17 days instead of
16 days. If Ganesh had worked alone after Ramesh
got sick, in how many days would he have
completed the remaining work?
(a) 13.5
(C) 12
(b) 11
(d) 14.5​

Answers

Answered by shrinkuashihuny
0

Answer:

13.4

Step-by-step explanation:

hope it helps u please follow me