Math, asked by hussain4102, 1 year ago

Ramesh and suresh can do a piece of work in 20 days and 12 days respectively. Ramesh started the work alone and then after 4 days, suresh joined him till the completion of the work. How long did the work last?

Answers

Answered by harsh2786
0

Answer:

9-3/5

Step-by-step explanation:

Ramesh ka ek din ka kaam=1/20

Suresh ka ek din ka kaam=1/12

Ramesh ka 4 din ka kaam=4/20=1/5

bacha hua kary =4/5

mana yah kary Ramesh dvara x din main Kiya jayega

: x/12=4/5

x =48/5 din

Answered by FelisFelis
1

The work last for 10 days.

Step-by-step explanation:

Consider the provided information.

Ramesh can do a piece of work in 20 days.

Work done in 1 day is: \frac{1}{20}

Ramesh started the work alone for 4 days.

The work done by Ramesh in 4 days are: \frac{4}{20}

Ramesh and suresh can do a piece of work in 20 days and 12 days respectively.

If they work together, then work done of 1 day is: \frac{1}{20}+\frac{1}{12}=\frac{8}{60}

Let they work together for x days.

\frac{4}{20}+x(\frac{8}{60}) =1

x(\frac{8}{60}) =1-\frac{4}{20}

x(\frac{8}{60}) =\frac{16}{20}

x=\frac{16}{20}\times\frac{60}{8}

x=6

Thus, together they work for 6 days.

Total number of days = 6 days + 4 days = 10 days

Hence, the work last for 10 days.