Math, asked by Sandeepranja, 10 months ago

ramesh can do a piece of work in 20 days how much work can he do in 5 days​

Answers

Answered by aditya6356
7

Step-by-step explanation:

ramesh can do a work =20days

but, in 1 day=1/20

therefore, how much work they do in a 5 days.

in 5 days=5/20

1/4 part of the work they do in a 5days.

Answered by ansariabuzar3662
0

Step-by-step explanation:

20/5=4 piece

PLZ MARK MY ANSWER AS BRAINLIEST