Ramesh can finish his work in 25 days, working 8 hours a day. If he wants to finish the same work in 20 days., how many hours should he work in a day?

Answers

Answered by neelimashorewala
18
working hours in one day = 8 
total days = 25 
so, total working hours = 25 × 8 = 200
now, he has to finish it in 20 days. 
so, 
total hours = 200 
no. of days required = 20 
working hours per day = 200 ÷ 20 = 10 

he needs to work 10 hours daily. 
Answered by Golda
13
Solution:-
The given data can be tabulated as below.
Work........25............20
Hours........8..............x
as days are decreased then hours will be increased. So, this is an inverse variation.
Therefore,
20*x = 25*8
⇒ x = 200/20
⇒ x = 10 hours 
So, Ramesh has to do per day 10 hours work to finish the same work in 20 days.