Ramit can finish his work in 25 days working 8 hours a day if he wants to finish the same work in 20 days how many hours should he work in a day ?​

Answers

Answered by sahasraramadugu2005
12

it so an indirect proportion as less the days more the time taken, hence 25×8=20×x

200=20x

200/20=x

10=x

thus, he will work 10 hours a day