Math, asked by abichal0, 9 months ago

Ramit can finish his work in 25 days, working eight hours a day.if he wants to finish the same work in 20days, how many hours should he work in a day?​

Answers

Answered by shubhamkr5923
11

Answer:

10 hour

Step-by-step explanation:

Simple.

Multiply hours and days to find out total number of hours necessary to complete the job. In this case it is 8 x 25 = 200. This job requires 200 hours of work.

If the person only has 20 days, then how many hours per day does he/she need to work? Just divide total hours to work by number of days. In this case 200 / 20 = 10

The answer is that Remit needs to work 10 hours a day to complete the same job in 20 days.