Randhir is 1 1/2 times faster than sudhir . If Randhir can complete a piece of work in 20 Days , how long will it take for both Randhir and Sudhir to complete the same piece of wrok ?
Answers
Answered by
5
Randhir can complete a piece of work in 20 Days
His rate of work per day = 1/20
Randhir is 1 1/2 times faster than Sudhir
Sudhir's = (1/20)/(1 1/2) = 1/30 per day
Their combined rate = 1/20 + 1/30
= 1/12 per day
Both Randhir and Sudhir working together will take:
1/ (1/12) = 12 days
Answered by
0
Answer:
Step-by-step explanation:
Randhir can complete a piece of work in 20 Days
His rate of work per day = 1/20
Randhir is 1 1/2 times faster than Sudhir
Sudhir's = (1/20)/(1 1/2) = 1/30 per day
Their combined rate = 1/20 + 1/30
= 1/12 per day
Both Randhir and Sudhir working together will take:
1/ (1/12) = 12 days