ravi can do 3/4 of a work in 12 days in how many days Ravi can finish the 1/2 work. ye right
Answers
Answered by
2
8 days ia your ans
plzzz
mark me
Attachments:
Answered by
0
Answer:
3/4 work can be done in 12 days
1/2,, ,, , , ,, ,, ,, 3/4×12×1/2=9/2 days
Step-by-step explanation: