Ravi can do a piece of work in 10 days, and Kamla can do the same work in 16 days. With the help of Reeta they do the work in 4 days only. In how many days can Reeta do the work alone?

Answers

Answered by Anonymous
2

Let's say we have 48 units of work.

A’s rate of work is 48/24 = 2 units per day

B's rate of work is 48/16 = 3 units per day

So looking at rates of work…

A+B+C = 48/8

2+3+C=6

C = 6-5

=1

C would complete the work in 48/1 = 48 days

Ans = 48days

Answered by Anonymous
1

Answer:

Hey mate..!!

YouR solution is..!!

Step-by-step explanation:

Let's say we have 48 units of work.

A’s rate of work is 48/24 = 2 units per day

B's rate of work is 48/16 = 3 units per day

So looking at rates of work…

A+B+C = 48/82+3+C=6C = 6-5=1C

would complete the work in 48/1 = 48 days

Answer = 48 days