ravi finishes a pieces of work in 8 days and dushyant finishes the same work in 10 days. how much time will they take to finish the work, if both work together
Answers
Answered by
13
No. of days Ravi finishes work in- 8
No. of days Dushyant finishes work - 10
Therefore,
1 day work of Ravi= 1/8
1 day work of dushyant = 1/10
1 day work of Ravi + dushyant= 1/8+1/10=18/80=9/40
Therefore,
They will complete work in 40/9 days ( reciprocal the answer)