Shashank, Sargur and Harsha are involved in a work. Shashank and Sargur can finish the work in 3
days. Sargur and Harsha can finish the work in 6 days and Shashank and Harsha can finish the work
in 12 days. In how many days Shashank alone can finish the work?
8 days
4 days
6 days
10 days​

Answers

Answered by Raavanmaharaj
2

Answer

Answer is 6 days.

Step-by-step explanation:

Let shashanks work be x,sargurs be y and z harshas be z.

given 1/x+1/y=1/3.......(1)

1/y+1/z=1/6........(2)

1/z+1/x=1/12........(3)

add all equations we will get

2[1/x+1/y+1/z]=7/12

=1/x+1/y+1/z=7/6( using equation 2)

we get 1/x=1/6.

Therefore, shashank alone can complete the work in 6 days.☺️☺️☺️