Rita and Mita together can do a work in 4 days. Rita
alone takes 6 days to do the same work. In how many
days can Mita alone do the work?
Answers
Answered by
0
Answer:
Simple answer 6 days.
Step-by-step explanation:
Rita alone takes 6 days then Mira will also need 6 days.
Answered by
30
Step-by-step explanation:
Work done by rita in one day=1/6
Work done by mita in one day=1/x
Work done by rita and mita together in one day=1/4
=1/4=1/6+1/x
=1/x=1/4-1/6
=1/x=(3-2)/12
=1/x=1/12
Therefore mita can complete the work in 12 days
Similar questions
English,
5 months ago
Political Science,
5 months ago
Math,
5 months ago
Math,
10 months ago
English,
10 months ago
English,
1 year ago
Biology,
1 year ago
Computer Science,
1 year ago