rohit and mohit can complete a task in 6 days and Misha can do it in 18 days. How much time will mohit take to complete it alone?
Answers
Answered by
1
Answer:
12 days
Step-by-step explanation:
2 people completed it in 6 days which is half of 12.
if Misha was alone and she completes her task in 18 days so if 2 people completed her task it would be 9 days